Question 1
Which of the following would not be considered a subsidiary plan of the project management plan?
The scope baseline is part of the project management plan; however, it isn't a subsidiary plan.
Question 2
You and your team have put together a comprehensive project management plan and you feel it will be executed effectively. What do you need to do before you can begin executing project work?
In this case, there may be several things you will do, including carrying out a kick-off meeting and explaining the plan to your customer. The project management plan needs to be formally bought into and accepted before you can begin execution.
Question 3
What is the main output of direct...