
Becoming a PMP® Certified Professional
By :

Question 1
Which of the following is the most common precedence relationship?
Question 2
You are working with your team and analyzing the current version of your precedence network diagram, as well as the durations that have been added to it. You are trying to figure out the critical path. Which of the following would be considered the near critical path?
Question 3
While planning a large installation project, your key resource lets you know that the first rollout will include tests for the system before the rest of the installations happen. He estimates that the automated tests will take about 5 hours to complete, and that it isn't necessary for him to be there when the testing occurs. Which of the following testing times could be considered?
Change the font size
Change margin width
Change background colour