8/80 rule of WBS: This is a rule of thumb used in the context of breaking down work from the scope into the schedule. Refer to Chapter 6, Work Breakdown Structure – the Single Critical Factor.
Accrue (field): Resource cost can be accrued either at the beginning of a task or as the work progresses (prorated), or at completion. The default value is Prorated
. The primary location of this field is the Resource Sheet. Refer to Chapter 5, Resource Management with Microsoft Project.
Actuals: This is an important detail of schedule progress tracking and can apply to work, cost, and overall progress. Before project execution is tracked, the actuals will only be planned (estimated) values. Refer to Chapter 13, Project Tracking Techniques.
Assignment: Allocation of a resource (this could be a person, machinery, equipment, or even a budgeted cost) to execute a task.
Automatically scheduled tasks: This is the recommended operating mode for tasks in Project...